Welcome to the podcast Inside 
SAP Esperana Cloud. 

2
00:00:15,080 --> 00:00:17,920
There is no customer success 
without product success and 

3
00:00:17,920 --> 00:00:21,160
project success. 
I'm Jerry Lowry, P&E Solution 

4
00:00:21,160 --> 00:00:24,280
Architects reporting SAP 
Esperana Cloud Public Edition, 

5
00:00:24,600 --> 00:00:26,280
and I'll be the host for today's
episode. 

6
00:00:26,880 --> 00:00:29,440
Today, we'll discuss the 
parallel line or PL. 

7
00:00:29,680 --> 00:00:33,040
implementation experience at one
of our SAP customers in the area

8
00:00:33,040 --> 00:00:36,400
of professional services at the 
support of the SAP partner 

9
00:00:36,400 --> 00:00:39,560
Emphasis. 
As our guest today, we have 

10
00:00:39,600 --> 00:00:43,880
Ajay, Senior Industry Principal 
from Emphasis and from SAP, we 

11
00:00:43,880 --> 00:00:47,520
have Nicola Pace, SAP Product 
Manager for S4 Honda Cloud 

12
00:00:47,520 --> 00:00:50,440
Public Edition and lead of the 
early Adopter program for the 

13
00:00:50,440 --> 00:00:53,960
parallel line and J Srinivasan, 
P&E Solution Architect 

14
00:00:54,080 --> 00:00:57,040
supporting SAP S4 Honda Cloud 
Public Edition and Regional 

15
00:00:57,040 --> 00:00:58,560
Point of Contact for the 
parallel line. 

16
00:00:58,920 --> 00:01:01,000
Welcome to you all. 
Let's start with a short 

17
00:01:01,000 --> 00:01:03,520
introduction. 
Some fun facts about you, You 

18
00:01:03,520 --> 00:01:05,760
first, Ajay. 
Thank you, Jerry. 

19
00:01:06,200 --> 00:01:11,280
I lead the services portfolio 
for Infosys for all SAP 

20
00:01:11,280 --> 00:01:14,000
engagements for customers across
the globe. 

21
00:01:14,280 --> 00:01:18,720
Over the last few years, I had 
the opportunity to deliver S4 

22
00:01:18,720 --> 00:01:22,240
HANA public Cloud LED finance 
transformation for our customers

23
00:01:22,240 --> 00:01:25,920
in this industry segment and 
still continuing that journey 

24
00:01:25,920 --> 00:01:28,280
with support from my clients and
SAP. 

25
00:01:29,000 --> 00:01:31,880
Funny thing, well, there is 
nothing much funny about me. 

26
00:01:32,280 --> 00:01:36,840
I try to be as focused on my 
work and therefore my colleagues

27
00:01:36,840 --> 00:01:39,720
and my friends always make fun 
of me about that fact. 

28
00:01:40,120 --> 00:01:41,160
Good to be here. 
Thank you. 

29
00:01:41,840 --> 00:01:44,720
Thanks, RJ. 
So great to have you Nicola. 

30
00:01:45,480 --> 00:01:48,120
Thanks a lot to Jerry. 
This is Nicola Pache. 

31
00:01:48,160 --> 00:01:52,480
I am from Product Management 
SCPS for HANA Cloud Public 

32
00:01:52,480 --> 00:01:58,240
Edition and well during the last
five years, I supported the go 

33
00:01:58,240 --> 00:02:02,200
to market first of the three 
system landscape architecture 

34
00:02:02,240 --> 00:02:04,640
for the Esfahana Cloud Public 
Edition. 

35
00:02:04,920 --> 00:02:09,160
Then I moved to the landscape 
extension called Parallel Line 

36
00:02:09,440 --> 00:02:13,400
by leading together with our 
colleague Darwin Talyarita, 2 

37
00:02:13,400 --> 00:02:17,160
early adopted programs that 
ended successfully with the 

38
00:02:17,160 --> 00:02:20,320
general availability of the 
three system landscape in 

39
00:02:20,320 --> 00:02:25,560
September 2022 and of the 
Parallel line in April 2025. 

40
00:02:26,280 --> 00:02:29,680
Indeed, I can say they have been
quite 5 interesting and 

41
00:02:29,680 --> 00:02:32,960
challenging years. 
Thank you, Nicola. 

42
00:02:33,560 --> 00:02:37,240
Jay, could you give us? 
Thanks so much for having us 

43
00:02:37,240 --> 00:02:39,840
today. 
I'm really excited to be here. 

44
00:02:40,280 --> 00:02:43,320
For the past eight years, I've 
been working as a solution 

45
00:02:43,320 --> 00:02:47,160
architect for SAPS for HANA 
Cloud Public Edition, helping 

46
00:02:47,160 --> 00:02:50,640
customers succeed with the 
implementation and deployment of

47
00:02:50,760 --> 00:02:52,880
SAPS for HANA Cloud Public 
Edition. 

48
00:02:53,440 --> 00:02:56,640
Currently, I'm serving as a 
region point of contact for 

49
00:02:56,640 --> 00:03:00,840
Parallel Line in North America. 
Outside of the tech world, I tap

50
00:03:00,840 --> 00:03:03,840
into my creative site right 
through writing and directing 

51
00:03:03,840 --> 00:03:05,600
short films. 
It's a passion that keeps me 

52
00:03:05,600 --> 00:03:08,560
inspired and also he was my 
fresh thinking and everything I 

53
00:03:08,560 --> 00:03:10,440
do. 
That's a little fun fact about. 

54
00:03:11,280 --> 00:03:12,280
That's great. 
Thank you, Jay. 

55
00:03:12,840 --> 00:03:16,560
OK, let's dive in. 
Jay, could you provide us a 

56
00:03:16,560 --> 00:03:19,200
quick introduction for our 
listeners about the parallel 

57
00:03:19,200 --> 00:03:21,840
line in SAP As for HANA Cloud 
Public Edition? 

58
00:03:22,440 --> 00:03:24,720
Sure, before. 
Elaborating, I think 1 should 

59
00:03:24,760 --> 00:03:27,640
need to understand what's a 
background and also the problem 

60
00:03:27,640 --> 00:03:31,240
which parallel line would solve.
Traditionally with ECC 

61
00:03:31,240 --> 00:03:33,640
applications right 
implementations, I have 

62
00:03:33,640 --> 00:03:37,160
encountered many customers who 
needed to perform various tasks 

63
00:03:37,240 --> 00:03:39,960
like project specific 
configurations, testing, 

64
00:03:39,960 --> 00:03:42,160
upgrades, data migration and 
also training. 

65
00:03:42,640 --> 00:03:45,960
These tasks often require a 
separate client within their 

66
00:03:45,960 --> 00:03:48,840
environment. 
With a move to SAPS for an 

67
00:03:48,840 --> 00:03:52,240
upload public edition and it's 3
system landscape, we now have a 

68
00:03:52,240 --> 00:03:55,560
more flexible solution called 
the Paddle line which allows the

69
00:03:55,560 --> 00:03:58,600
customer to perform the tasks 
like project specific 

70
00:03:58,600 --> 00:04:01,280
configuration, testing, upgrades
and data migrations. 

71
00:04:01,360 --> 00:04:03,760
That's the advantage of having a
pallet line. 

72
00:04:04,360 --> 00:04:07,400
That sounds very interesting. 
Could you put a little more 

73
00:04:07,400 --> 00:04:10,600
color on what is the? 
Pallet line, Yeah, absolutely. 

74
00:04:10,880 --> 00:04:13,600
The pallet line is a 
state-of-the-art offspring that 

75
00:04:13,600 --> 00:04:16,640
provides enhanced flexibility 
within SAPS for HANA Cloud 

76
00:04:16,640 --> 00:04:20,640
Public Edition actually became 
available to SAPS HANA Cloud 

77
00:04:20,640 --> 00:04:24,480
Public Edition customers using a
three system landscape as of 

78
00:04:24,680 --> 00:04:27,880
April 1st, 2025. 
Essentially, it offers a 

79
00:04:27,880 --> 00:04:31,520
separate workspace in SAP 
Central Business configuration, 

80
00:04:31,720 --> 00:04:36,160
including two additional tenants
for configuration like D120 and 

81
00:04:36,160 --> 00:04:40,120
the testing environment D120. 
This has been a long running ask

82
00:04:40,120 --> 00:04:42,800
from a lot of our customers. 
So what can customers do with 

83
00:04:42,800 --> 00:04:46,440
these additional tenants? 
As I stated earlier, the paddle 

84
00:04:46,440 --> 00:04:50,480
line allows customers to test to
validate scope extensions, roll 

85
00:04:50,480 --> 00:04:54,200
out new countries, we can extend
organizational structures, 

86
00:04:54,400 --> 00:04:57,920
perform data migration, build 
and test integrations, and 

87
00:04:57,920 --> 00:05:01,880
contact training and testing. 
The beauty of it is that all 

88
00:05:01,880 --> 00:05:05,440
these activities can be done 
without any disruptions to the 

89
00:05:05,440 --> 00:05:08,400
main project line. 
Yes, that sounds like a 

90
00:05:08,400 --> 00:05:11,120
significant advantage. 
How does this help, especially 

91
00:05:11,120 --> 00:05:12,720
during critical event cycle? 
Upgrades. 

92
00:05:13,360 --> 00:05:16,640
Indeed, it's particularly. 
Useful during the upgrades when 

93
00:05:16,640 --> 00:05:19,160
as we have seen by when you 
innovations are introduced, 

94
00:05:19,840 --> 00:05:23,040
customers can test and validate 
these changes to the parallel 

95
00:05:23,040 --> 00:05:25,520
line without affecting their 
main line of business. 

96
00:05:25,840 --> 00:05:29,120
This ensures A smoother 
transition and minimize this 

97
00:05:29,120 --> 00:05:31,200
risk. 
I could see, yes. 

98
00:05:31,240 --> 00:05:34,800
So help me understand, is this 
feature only beneficial for live

99
00:05:34,800 --> 00:05:37,120
customers or could new 
implementations also take 

100
00:05:37,120 --> 00:05:39,280
advantage? 
I could imagine this would be 

101
00:05:39,320 --> 00:05:41,800
particularly useful for cutovers
and migration testing. 

102
00:05:42,400 --> 00:05:45,040
You're right again, it's not 
just for the live customers. 

103
00:05:45,280 --> 00:05:47,840
Even those in the middle of 
their implementation can 

104
00:05:47,840 --> 00:05:51,720
leverage parallel line for data 
migration test, haddock training

105
00:05:51,720 --> 00:05:55,520
or any other testing needs as 
long the prerequisites are 

106
00:05:55,520 --> 00:05:58,040
satisfied. 
It is designed to offer 

107
00:05:58,080 --> 00:06:01,200
flexibility at any stage of the 
project life cycle and making 

108
00:06:01,200 --> 00:06:02,880
the entire process more 
efficient. 

109
00:06:03,920 --> 00:06:07,400
And turning to Nicola, I imagine
you have significant insight 

110
00:06:07,480 --> 00:06:10,200
considering your experience. 
Do you want to add anything? 

111
00:06:11,240 --> 00:06:13,960
Yes, Jerry. 
Well, as I also have recently 

112
00:06:13,960 --> 00:06:18,240
described in an article on 
LinkedIn with the introduction 

113
00:06:18,240 --> 00:06:22,160
to the market of the three 
system landscape, SAP made 

114
00:06:22,240 --> 00:06:26,600
already three years ago a big 
step ahead in the cloud ERP 

115
00:06:26,640 --> 00:06:29,760
space. 
This three system Landscape new 

116
00:06:29,760 --> 00:06:34,200
architecture fulfilled most of 
the requirements raised by 

117
00:06:34,200 --> 00:06:38,080
customers after the previous 
launch of the two system 

118
00:06:38,080 --> 00:06:42,080
landscape and the three system 
granted among all other 

119
00:06:42,080 --> 00:06:46,480
improvements also new 
fundamental capabilities like 

120
00:06:46,520 --> 00:06:50,640
more extensibility, more 
configurability of the solution,

121
00:06:50,920 --> 00:06:55,520
control on content deployment to
the productive environment. 

122
00:06:55,800 --> 00:07:00,320
It also offer more separation of
concern between development and 

123
00:07:00,320 --> 00:07:02,920
test which into a cell were 
combined. 

124
00:07:03,520 --> 00:07:07,840
It also grants full continuity 
for project activities during 

125
00:07:07,840 --> 00:07:12,120
the software upgrade cycles. 
After the general availability 

126
00:07:12,160 --> 00:07:17,040
of this three system landscape, 
however, SAP started collecting 

127
00:07:17,040 --> 00:07:20,440
additional requirements also for
this three system landscape 

128
00:07:20,440 --> 00:07:23,720
architecture. 
That brought us to the concept 

129
00:07:23,760 --> 00:07:27,800
of the parallel line. 
This architectural enhancement 

130
00:07:28,040 --> 00:07:33,840
is intended on one side to offer
more runs of the same activities

131
00:07:33,840 --> 00:07:37,600
like data migration and testing 
in a separate environment. 

132
00:07:38,160 --> 00:07:41,720
On the other side, even more 
importantly, grants the 

133
00:07:41,720 --> 00:07:45,640
separation of subsequent 
configuration projects from the 

134
00:07:45,640 --> 00:07:49,760
life cycle events that are 
continuously innovating the 

135
00:07:49,760 --> 00:07:53,080
productive environment. 
So we can say that the parallel 

136
00:07:53,080 --> 00:07:57,240
line offers the implementation 
team the capability to run 

137
00:07:57,400 --> 00:08:01,520
parallel configuration projects 
in separate environment with 

138
00:08:01,520 --> 00:08:06,240
different timing for deployment,
the configuration to mainline 

139
00:08:06,440 --> 00:08:09,720
and to production. 
Nicola, thank you. 

140
00:08:09,720 --> 00:08:12,280
So this is very insightful. 
Let's turn to AJ. 

141
00:08:12,320 --> 00:08:16,320
So AJ, could you explain a bit 
about emphasis experience with 

142
00:08:16,320 --> 00:08:18,320
customers and implementing the 
parallel line? 

143
00:08:18,760 --> 00:08:21,640
What kind of businesses are they
in and what was the scope of the

144
00:08:21,640 --> 00:08:23,560
implementation? 
Thank you, Jerry. 

145
00:08:23,640 --> 00:08:28,120
I would echo the statements made
by Nicola and Jay. 

146
00:08:28,320 --> 00:08:32,080
The S 400 cloud product has 
evolved over a period of time 

147
00:08:32,080 --> 00:08:36,520
starting with the basic 2SL with
manager solution and a set of 

148
00:08:36,520 --> 00:08:40,120
SSU is. 
Then it was further enhanced 

149
00:08:40,120 --> 00:08:43,000
with the central business 
configuration within the two SL 

150
00:08:43,159 --> 00:08:46,240
where you could have those 
control deployments and then 

151
00:08:46,240 --> 00:08:50,280
enable that. 
Subsequently, TSL was enabled 

152
00:08:50,280 --> 00:08:53,880
and now we have the Parallel 
Line and this whole journey 

153
00:08:53,880 --> 00:08:57,520
indicates that the aim is to 
bring parity between the cloud 

154
00:08:57,520 --> 00:09:01,640
capability and what most of the 
customers who are in this cloud 

155
00:09:01,640 --> 00:09:05,520
journey expect. 
Our experience with Parallel 

156
00:09:05,520 --> 00:09:09,600
Line is for a leading services 
firm with operations in 40 plus 

157
00:09:09,600 --> 00:09:13,840
countries where their leverage 
is for HANA Public Cloud as the 

158
00:09:13,840 --> 00:09:16,240
centrepiece for their finance 
transformation. 

159
00:09:16,960 --> 00:09:21,520
And the use case is pretty much 
everything which Jay and Nicola 

160
00:09:21,520 --> 00:09:25,200
elaborated, be it for multiple 
rounds of data migration, to 

161
00:09:25,200 --> 00:09:29,560
validate data in a clean 
environment or with a multiple 

162
00:09:29,560 --> 00:09:32,960
phased roll out, how do they 
efficiently and effectively 

163
00:09:32,960 --> 00:09:37,480
manage the operations and the 
continuing roll outs, How do you

164
00:09:37,480 --> 00:09:39,600
enable that? 
And the centrepiece of that is 

165
00:09:39,600 --> 00:09:41,400
going to be the Parallel Line 
environment. 

166
00:09:42,280 --> 00:09:42,960
I see. 
I see. 

167
00:09:43,000 --> 00:09:43,560
OK. 
Thank you. 

168
00:09:43,600 --> 00:09:46,840
Ajay. 
Jay, are there any prerequisites

169
00:09:46,840 --> 00:09:48,360
for implementing the parallel 
line? 

170
00:09:49,080 --> 00:09:52,360
Yes, Jerry, again, if a customer
would like to implement parallel

171
00:09:52,360 --> 00:09:54,840
line, there are certain 
prerequisite checks which have 

172
00:09:54,840 --> 00:09:57,000
to be met and it includes the 
following. 

173
00:09:57,000 --> 00:09:59,240
Again, these are the 
prerequisites checks which are 

174
00:09:59,240 --> 00:10:02,640
being defined as of now. 
So the first one would be that 

175
00:10:02,640 --> 00:10:04,440
the production tenant must be 
provisioned. 

176
00:10:04,960 --> 00:10:09,440
The second, all CBC and BC 
transports in the customizing 

177
00:10:09,440 --> 00:10:12,040
tenant should be released from 
the customizing tenant. 

178
00:10:12,040 --> 00:10:14,640
I'm talking about the transports
in the main line, right? 

179
00:10:15,400 --> 00:10:19,240
The 3rd, all the transports in 
the import buffer of the test 

180
00:10:19,240 --> 00:10:23,880
segment should be imported. 
Finally, the mainline workspace 

181
00:10:23,880 --> 00:10:27,960
in CPC, all the activities and 
milestones of the scope and 

182
00:10:27,960 --> 00:10:31,640
organization structure phase 
should be in completed status 

183
00:10:32,040 --> 00:10:34,800
and the mainline workspace 
should be in the product 

184
00:10:34,800 --> 00:10:37,680
specific configuration phase and
it should be unlocked. 

185
00:10:38,320 --> 00:10:41,960
And again, this please request 
check must be requested by the 

186
00:10:41,960 --> 00:10:46,040
customer using SAP for me. 
Once the prerequisite checks are

187
00:10:46,040 --> 00:10:49,960
met, the customer will receive a
notification e-mail in their 

188
00:10:50,000 --> 00:10:53,880
inbox and the service request 
will be updated in SAP for me. 

189
00:10:54,000 --> 00:10:57,680
Then the customer can create a 
service request to initiate the 

190
00:10:57,680 --> 00:10:59,640
branch and then follow the 
process. 

191
00:11:00,240 --> 00:11:01,440
Great. 
OK, thanks, Jay. 

192
00:11:01,440 --> 00:11:05,640
I think that's very clear. 
Ajay, could you please share why

193
00:11:05,640 --> 00:11:08,520
did the customer choose to 
implement the parallel line for 

194
00:11:08,520 --> 00:11:10,200
this project? 
Sure. 

195
00:11:10,640 --> 00:11:14,640
This customer has a global 
business operations with spread 

196
00:11:14,640 --> 00:11:18,920
in 40 countries and given the 
complex nature of their 

197
00:11:18,920 --> 00:11:22,600
organization, it wasn't feasible
for them to do a Big Bang Golie 

198
00:11:22,960 --> 00:11:27,400
and therefore as a part of the 
Golie, we evolved on a phased 

199
00:11:27,440 --> 00:11:30,920
Goliev. 
Now with the phase go live, it 

200
00:11:30,920 --> 00:11:34,960
brings certain aspects during 
the program and go live of the 

201
00:11:34,960 --> 00:11:38,120
initial phase. 
For example, during the program 

202
00:11:38,160 --> 00:11:41,880
with multiple phases, we need to
manage multiple rounds of data 

203
00:11:41,880 --> 00:11:45,400
migration both for the initial 
phase as well As for the 

204
00:11:45,400 --> 00:11:49,480
subsequent phases. 
Now in three system landscape 

205
00:11:49,640 --> 00:11:53,640
where you didn't have the 
provision like an on Prem to 

206
00:11:53,720 --> 00:11:56,520
refresh the database because 
customers come from that 

207
00:11:56,520 --> 00:12:00,640
mentality, how do you satisfy 
the need for them to do multiple

208
00:12:00,640 --> 00:12:03,760
rounds of data migration and 
that's where parallel line comes

209
00:12:03,760 --> 00:12:05,800
into play. 
So that's the first use case for

210
00:12:05,800 --> 00:12:08,960
this customer. 
Second, I mentioned about the 

211
00:12:08,960 --> 00:12:12,920
rollouts where multiple rollouts
are planned for this customer. 

212
00:12:13,240 --> 00:12:16,840
We are starting with the initial
goal live in this November and 

213
00:12:16,840 --> 00:12:21,520
then next year which is 2026, 
there are about three goal as 

214
00:12:21,520 --> 00:12:24,640
planned and then subsequently in
2027 few more goal lives are 

215
00:12:24,640 --> 00:12:27,680
planned. 
Now with multiple goal lines, 

216
00:12:27,840 --> 00:12:32,160
how do we manage the operations 
and the rollouts efficiently? 

217
00:12:32,160 --> 00:12:34,720
How do we bring the 
differentiation where we can 

218
00:12:34,720 --> 00:12:38,760
provide priority for anything 
which impacts operations while 

219
00:12:38,760 --> 00:12:40,360
maintaining the project 
schedule? 

220
00:12:40,840 --> 00:12:44,080
That's the second use case for 
parallel line where we will be 

221
00:12:44,080 --> 00:12:48,760
able to focus on specific tasks 
as a part of the parallel line 

222
00:12:48,760 --> 00:12:51,800
and then deal the main line for 
other set of tasks. 

223
00:12:52,600 --> 00:12:58,000
The third aspect why we decided 
to consider the parallel line is

224
00:12:58,000 --> 00:13:02,800
on localization with the 40 
countries and of course some 

225
00:13:03,040 --> 00:13:07,000
unsupported SAP countries. 
How do we ensure that the 

226
00:13:07,000 --> 00:13:10,760
program is not at risk while 
accidentally activating 

227
00:13:10,760 --> 00:13:14,800
something which can then put the
entire program in jeopardy? 

228
00:13:15,320 --> 00:13:18,760
That's under use case for 
parallel line where we could 

229
00:13:18,760 --> 00:13:22,960
activate new countries, check 
their localizations, validate it

230
00:13:23,080 --> 00:13:24,680
before we do it in the main 
line. 

231
00:13:25,160 --> 00:13:30,760
Because parallel line gives us 
the ability to rebranch as many 

232
00:13:30,760 --> 00:13:34,960
number of times as we need. 
For example, if I stand up the 

233
00:13:34,960 --> 00:13:40,160
parallel line today and I did a 
set of tasks, I found that 

234
00:13:40,160 --> 00:13:43,520
something is wrong and I will 
not be able to use that parallel

235
00:13:43,520 --> 00:13:48,040
line any further. 
I am able to bring down that 

236
00:13:48,800 --> 00:13:52,160
client and stand it up again 
with the latest copy and 

237
00:13:52,160 --> 00:13:57,280
therefore it helps me validate 
certain of certain edge use 

238
00:13:57,280 --> 00:14:01,000
cases or edge localizations 
without impacting the program. 

239
00:14:01,520 --> 00:14:05,720
These are some of the examples 
and needs which we thought 

240
00:14:05,720 --> 00:14:11,720
through and chose to go with the
Parallel Line project. 

241
00:14:12,000 --> 00:14:14,880
Jerry. 
Thanks, Ajay. 

242
00:14:14,880 --> 00:14:17,720
That makes a lot of sense. 
And you know, we can see that it

243
00:14:17,720 --> 00:14:20,200
seems the customer experience 
was pretty good and they 

244
00:14:20,200 --> 00:14:24,880
certainly, you know, received a 
lot of benefit from from the 

245
00:14:24,880 --> 00:14:26,760
parallel line and it really 
helped their project. 

246
00:14:26,760 --> 00:14:30,440
So maybe a two-part question, 
where are they at today? 

247
00:14:30,440 --> 00:14:32,600
So what's the status update on 
the project? 

248
00:14:32,880 --> 00:14:35,400
And could you also, you know, 
second part, walk us through 

249
00:14:35,400 --> 00:14:37,640
some of the various steps and 
share some of the experiences so

250
00:14:37,640 --> 00:14:39,680
far? 
Sure. 

251
00:14:40,840 --> 00:14:46,040
We started this program last 
last year the sometime made of 

252
00:14:46,680 --> 00:14:49,920
2024. 
We finished our design and then 

253
00:14:49,920 --> 00:14:54,320
we started the build in 2025. 
We are nearing the completion of

254
00:14:54,320 --> 00:14:58,160
build and then starting the 
testing in about a couple of 

255
00:14:58,160 --> 00:15:01,000
weeks with the aim to go live 
towards the end of this year 

256
00:15:01,400 --> 00:15:04,440
followed by rollouts starting 
next year. 

257
00:15:04,440 --> 00:15:08,280
So 2026 and 2027 is going to be 
full of rollouts. 

258
00:15:08,760 --> 00:15:11,320
That's essentially that's 
essentially the status of the 

259
00:15:11,320 --> 00:15:14,080
program. 
So from an Activate perspective,

260
00:15:14,640 --> 00:15:17,320
we are currently in the realized
phase of the Activate 

261
00:15:17,320 --> 00:15:21,560
methodology and we will soon be 
in the deploy and then run and 

262
00:15:21,560 --> 00:15:26,320
of course the rollouts will 
start our experience, our 

263
00:15:26,320 --> 00:15:29,120
experience with parallel line or
if I have to talk about the 

264
00:15:29,120 --> 00:15:32,920
step, the very first step in the
process is to understand how 

265
00:15:32,920 --> 00:15:37,920
does parallel line work, what it
can do, what it cannot do, what 

266
00:15:37,920 --> 00:15:40,880
are what are the three 
requisites and how do we go 

267
00:15:40,880 --> 00:15:45,320
about with the process. 
It starts with enabling as Jay 

268
00:15:45,320 --> 00:15:48,840
mentioned earlier in this 
session, it starts with enabling

269
00:15:48,840 --> 00:15:51,200
the parallel line we were 
earlier adopted. 

270
00:15:51,200 --> 00:15:54,960
Therefore Nicola and team helped
us through a set of processes. 

271
00:15:54,960 --> 00:15:59,400
But now it's AG solution is in 
general level GA and therefore 

272
00:15:59,600 --> 00:16:02,640
customers have to raise a 
request and as a part of the 

273
00:16:02,640 --> 00:16:07,080
request there are pre checks 
done wherein the transports, it 

274
00:16:07,080 --> 00:16:09,040
is verified with the transports 
are In Sync. 

275
00:16:09,040 --> 00:16:12,040
If all the changes have been 
migrated and then if those pre 

276
00:16:12,040 --> 00:16:15,160
checks are done then customer we
raise the request. 

277
00:16:15,720 --> 00:16:19,880
You get the tenant provisioned 
within one day and once the 

278
00:16:19,880 --> 00:16:22,880
tenant is provisioned there are 
set of post processing 

279
00:16:22,880 --> 00:16:26,760
activities. 
Example the parallel line works 

280
00:16:26,760 --> 00:16:31,160
through a table copy which means
all the config data is copied 

281
00:16:31,240 --> 00:16:36,960
from the existing mainline 
tenants DNT to a parallel dev 

282
00:16:36,960 --> 00:16:39,760
and test tenant. 
However the reference data of 

283
00:16:39,760 --> 00:16:42,920
the config is not copied. 
So as a part of the post 

284
00:16:42,920 --> 00:16:47,560
processing, we will have to do 
that and we have to load the 

285
00:16:47,560 --> 00:16:51,120
data which is all the reference 
data apart from the reference 

286
00:16:51,120 --> 00:16:54,880
data to make the processes work.
In the parallel line, there may 

287
00:16:54,880 --> 00:16:57,720
be additional data which may be 
required for examples, you may 

288
00:16:57,720 --> 00:17:01,880
have to create some test data 
like customers, like projects 

289
00:17:01,880 --> 00:17:05,880
like sales, orders and etcetera.
Those are the things which we 

290
00:17:05,880 --> 00:17:07,319
have to be which we have to 
create. 

291
00:17:07,720 --> 00:17:11,480
So we went through this process,
validated it, and then once we 

292
00:17:11,480 --> 00:17:15,520
do a basic testing, we feel that
the parallel line is usable and 

293
00:17:15,520 --> 00:17:18,520
then we release it for the use, 
for the purpose. 

294
00:17:18,520 --> 00:17:23,119
For example, we get one cycle 
for data migration and that's 

295
00:17:23,119 --> 00:17:25,599
when we release it for 
subsequent rounds of data 

296
00:17:25,599 --> 00:17:30,760
migration. 
And once you do this as a as a 

297
00:17:30,760 --> 00:17:34,920
step one, the next important 
step we do is to keep the lines 

298
00:17:34,920 --> 00:17:39,880
In Sync before the main line. 
We have a habit or a practice of

299
00:17:40,360 --> 00:17:43,280
moving the transports every 
every fortnight, which means 

300
00:17:43,280 --> 00:17:47,080
every alternate week we move the
transports and keep all the 

301
00:17:47,080 --> 00:17:50,960
systems In Sync. 
This is to ensure that the 

302
00:17:50,960 --> 00:17:55,600
systems are In Sync and all the 
monthly patches and upgrades 

303
00:17:55,600 --> 00:17:59,480
which happened by SAP as a part 
of hot fix or other maintenance 

304
00:17:59,920 --> 00:18:02,400
is delivered which is delivered 
to all the systems. 

305
00:18:02,840 --> 00:18:05,640
It's not delivered in different 
versions for different system, 

306
00:18:05,800 --> 00:18:09,120
thereby resulting in some 
potential errors at a later 

307
00:18:09,120 --> 00:18:12,520
point in time. 
We extended that concept to the 

308
00:18:12,520 --> 00:18:16,840
parallel line and therefore what
we do once we sync the main 

309
00:18:16,840 --> 00:18:20,200
line, the following week we sync
the parallel line and that's 

310
00:18:20,200 --> 00:18:23,920
when we do the rebase and the 
merge, which means whatever is 

311
00:18:23,920 --> 00:18:26,880
work is done on the main line, 
we copy that to the parallel 

312
00:18:26,880 --> 00:18:30,280
line. 
And if we did some validations 

313
00:18:30,280 --> 00:18:33,640
or new solutions in the parallel
line and we find it to be 

314
00:18:33,920 --> 00:18:36,440
acceptable, we do a merge to the
main line. 

315
00:18:37,240 --> 00:18:39,800
And that's that's the second 
step of the process, which we 

316
00:18:39,800 --> 00:18:41,920
do. 
And the third step is we 

317
00:18:41,920 --> 00:18:47,680
periodically evaluate as to when
we should do a RE branch. 

318
00:18:47,880 --> 00:18:51,320
When we initially set up the 
environment, we did a RE branch.

319
00:18:52,080 --> 00:18:55,600
Subsequently, we used it, we 
activated few countries, we 

320
00:18:55,600 --> 00:18:59,080
tested the processes, but and 
then the main lane continued 

321
00:18:59,080 --> 00:19:01,760
with set of other set of 
configurations. 

322
00:19:02,240 --> 00:19:05,880
Now for data migration, we 
wanted a clean set of an clean 

323
00:19:05,880 --> 00:19:07,760
environment with all the 
configs. 

324
00:19:08,200 --> 00:19:11,080
That's when we decided that we 
should do a rebranch. 

325
00:19:11,480 --> 00:19:15,160
So the third step is to decide 
what would be the appropriate 

326
00:19:15,440 --> 00:19:18,840
time to do a rebranch. 
And in all this process it is 

327
00:19:18,840 --> 00:19:23,080
important to consider the lead 
times taken for this, build that

328
00:19:23,080 --> 00:19:25,840
into the project plan. 
That has been our learning and 

329
00:19:25,840 --> 00:19:29,560
the experience of how we went 
about approaching the parallel 

330
00:19:29,560 --> 00:19:32,000
line. 
We did have our share of 

331
00:19:32,480 --> 00:19:35,600
challenges in understanding and 
trying to work it through, but 

332
00:19:35,600 --> 00:19:38,640
that's part and parcel of any 
project, yeah. 

333
00:19:38,920 --> 00:19:42,200
Awesome awesome Ajay, thanks for
sharing your experiences. 

334
00:19:42,560 --> 00:19:46,360
Like one thing, I would advise 
the customers to regularly 

335
00:19:46,360 --> 00:19:49,560
synchronize the parallel line 
with the main line using the 

336
00:19:49,560 --> 00:19:51,840
rebase function. 
I think that's a practice that 

337
00:19:51,840 --> 00:19:53,960
would help them prevent any 
conflicts. 

338
00:19:54,440 --> 00:19:57,320
Moreover, during the project 
implementation in the in the 

339
00:19:57,320 --> 00:20:01,000
parallel line, it is recommended
to avoid making major conflict 

340
00:20:01,000 --> 00:20:03,200
changes in the directly in the 
main line. 

341
00:20:03,520 --> 00:20:07,280
This approach we know promotes 
more stable and manageable 

342
00:20:07,280 --> 00:20:11,560
processes. 
I think Nicola would agree to 

343
00:20:11,560 --> 00:20:12,720
that. 
Is there any other 

344
00:20:12,720 --> 00:20:14,400
recommendations for our 
business? 

345
00:20:14,520 --> 00:20:17,240
Nicola I. 
Would agree Jay. 

346
00:20:17,640 --> 00:20:21,680
Moreover, let me please add also
that together with development 

347
00:20:21,680 --> 00:20:26,840
and integration, the good 
practice of performing a regular

348
00:20:26,840 --> 00:20:33,240
rebase is also strictly related 
to creating the right 

349
00:20:33,320 --> 00:20:37,040
configuration conditions in the 
target system. 

350
00:20:37,440 --> 00:20:43,480
So in essence, with the rebase, 
the parallel line gets regularly

351
00:20:43,480 --> 00:20:48,040
synchronized with any 
configuration that is being made

352
00:20:48,040 --> 00:20:52,240
meanwhile in the main line. 
And this helps primarily for two

353
00:20:52,240 --> 00:20:56,080
reasons. 
Number one, that any validation 

354
00:20:56,360 --> 00:21:00,920
happening during test in the 
parallel line is more reliable 

355
00:21:01,200 --> 00:21:04,760
because the condition of 
existing configuration in the 

356
00:21:04,760 --> 00:21:09,560
parallel line reproduced more 
loyally the one in main line. 

357
00:21:10,160 --> 00:21:14,040
And #2 that all incremental 
configuration which are done in 

358
00:21:14,040 --> 00:21:18,520
the parallel line has more 
chance of success and not 

359
00:21:18,600 --> 00:21:22,840
generating conflicts when they 
will be merged to the main line,

360
00:21:23,080 --> 00:21:27,520
because they will find their 
very similar conditions in terms

361
00:21:27,520 --> 00:21:31,080
of configuration. 
Exactly same condition in terms 

362
00:21:31,080 --> 00:21:34,800
of configuration. 
This ensures correctness in the 

363
00:21:34,800 --> 00:21:37,640
merge as well. 
OK. 

364
00:21:37,680 --> 00:21:40,400
OK, Nicola, let's stick with 
you. 

365
00:21:41,400 --> 00:21:43,640
Let's talk about the future of 
the parallel line. 

366
00:21:43,640 --> 00:21:45,480
What do you think could be 
improved in future PL. 

367
00:21:45,480 --> 00:21:47,680
implementations and in the 
product itself? 

368
00:21:49,480 --> 00:21:53,800
It's great question because with
the general availability, Jerry 

369
00:21:53,800 --> 00:21:57,440
of the parallel line, we, I 
think we believe we reached only

370
00:21:57,440 --> 00:22:01,760
the very first to stay, only the
very first milestone and much, 

371
00:22:01,760 --> 00:22:05,720
much more is on the plan in the 
next weeks. 

372
00:22:05,720 --> 00:22:09,520
We have to strengthen clearly 
and make fully robust the 

373
00:22:09,520 --> 00:22:14,760
operational steps execution for 
branch and all the incremental 

374
00:22:14,760 --> 00:22:18,920
configuration synchronization to
which happens during rebase and 

375
00:22:18,920 --> 00:22:21,600
merge. 
We have to make them robust. 

376
00:22:21,720 --> 00:22:26,760
We have to make them completely 
consumable as a self-service by 

377
00:22:26,760 --> 00:22:30,160
the customer. 
In the short term, it's true we 

378
00:22:30,160 --> 00:22:35,760
also target to allow customers 
to replicate the parallel line 

379
00:22:35,800 --> 00:22:41,400
attendant specific extensibility
artifacts and to build also with

380
00:22:41,400 --> 00:22:46,560
very low effort those master 
data which are required during 

381
00:22:46,560 --> 00:22:49,360
the consumption of the parallel 
line tenants. 

382
00:22:50,560 --> 00:22:56,760
One additional target we have is
that while today the merge is 

383
00:22:56,760 --> 00:23:02,280
offered as full or none, meaning
whatever is being built in the 

384
00:23:02,280 --> 00:23:06,960
parallel line gets replicated to
the main line once merge is 

385
00:23:06,960 --> 00:23:09,640
executed. 
In the mid term. 

386
00:23:09,680 --> 00:23:13,800
Our ambition is to offer the 
so-called selective merge, 

387
00:23:14,320 --> 00:23:18,960
meaning that we want to allow 
customers to to select from the 

388
00:23:19,240 --> 00:23:24,280
parallel line only a portion of 
the incremental configuration 

389
00:23:24,280 --> 00:23:29,400
which they built, for example, 
only one country out of two and 

390
00:23:29,400 --> 00:23:34,120
have it replicated to the main 
line only one and not the full 

391
00:23:34,120 --> 00:23:36,800
configuration. 
This at the moment is still not 

392
00:23:36,800 --> 00:23:41,160
possible, but we're working to 
make it possible in the midterm.

393
00:23:41,560 --> 00:23:45,920
And the other major pillar of 
our road map for the parallel 

394
00:23:45,920 --> 00:23:50,760
line is to offer customers 
multiple parallel lines at the 

395
00:23:50,760 --> 00:23:55,320
same times, so that this can 
serve customer needs for 

396
00:23:55,320 --> 00:23:58,680
different purposes, different 
use cases, different 

397
00:23:58,680 --> 00:24:01,080
implementation projects at the 
same time. 

398
00:24:04,520 --> 00:24:06,120
Yeah, I could see that could be 
very great. 

399
00:24:06,280 --> 00:24:07,080
Thanks. 
Thanks. 

400
00:24:07,080 --> 00:24:10,240
Nicola. 
Ajay, speaking from the point of

401
00:24:10,240 --> 00:24:12,840
view as a partner, what was your
experience with the 

402
00:24:12,840 --> 00:24:15,960
implementation and were there 
any particular challenges that 

403
00:24:15,960 --> 00:24:18,200
stood out to you? 
Thank you, Jerry. 

404
00:24:18,520 --> 00:24:22,280
Our experience as I mentioned 
earlier, initially it was a 

405
00:24:22,280 --> 00:24:26,400
learning experience. 
The parallel line at that point 

406
00:24:26,400 --> 00:24:30,520
as a part of earlier doctor was 
available under two options. 

407
00:24:30,520 --> 00:24:34,880
So we had to we discussed with 
Nicola and team and then took 

408
00:24:34,880 --> 00:24:38,480
their guidance in terms of which
option to choose. 

409
00:24:38,520 --> 00:24:41,640
And then we went out for the 
table copy option. 

410
00:24:42,120 --> 00:24:48,720
And once we set that up, I think
we had our set of expectations 

411
00:24:48,720 --> 00:24:53,720
or wish list as I may call. 
And what we realized is that why

412
00:24:54,120 --> 00:24:57,280
the solution does offer a bit of
capabilities. 

413
00:24:57,280 --> 00:25:01,760
It is important to plan the post
processing which I elaborated. 

414
00:25:01,760 --> 00:25:05,480
For example, we should have 
sufficient task in the project 

415
00:25:05,480 --> 00:25:09,400
plan and sufficient time in the 
project plan to allow for the 

416
00:25:09,400 --> 00:25:12,800
post processing be it copying 
the reference master data which 

417
00:25:12,800 --> 00:25:19,080
is there in the OR even set up 
of basic data to validate that 

418
00:25:19,080 --> 00:25:21,200
the parallel line is set up 
properly. 

419
00:25:21,720 --> 00:25:24,560
Let's say we should have ready 
made templates for let's say 

420
00:25:24,560 --> 00:25:28,880
LTMCS for customers, project 
sales, orders, materials which 

421
00:25:28,880 --> 00:25:32,560
may be required to test. 
So those set of preparation has 

422
00:25:32,560 --> 00:25:36,640
to be done and then we should 
request this line so that once 

423
00:25:36,800 --> 00:25:41,400
the parallel line is available, 
we are able to effectively use 

424
00:25:41,400 --> 00:25:46,320
it and use it soon instead of 
trying to spend time in getting 

425
00:25:46,320 --> 00:25:48,480
it ready. 
So that's one key experience 

426
00:25:48,920 --> 00:25:53,120
which we had as a part of our 
adoption. 

427
00:25:53,600 --> 00:25:57,920
The second is in terms of the 
Mudge and the rebase frequency 

428
00:25:57,920 --> 00:26:01,880
itself and both Nikola and Jai 
articulated about it. 

429
00:26:02,040 --> 00:26:05,560
We had the experience where we 
were going through the country 

430
00:26:05,560 --> 00:26:08,440
activations. 
I mentioned we had about 40 plus

431
00:26:08,440 --> 00:26:11,440
countries. 
So our Sprint cycles in every 

432
00:26:11,440 --> 00:26:13,520
Sprint we take about 8 
countries. 

433
00:26:13,520 --> 00:26:19,040
We had about 5 to 6 prints. 
Now after and going by the SAP 

434
00:26:19,040 --> 00:26:22,200
best factors, we didn't activate
more than five countries. 

435
00:26:22,640 --> 00:26:26,720
So we had the parallel line we 
set up, we set up all the four, 

436
00:26:26,720 --> 00:26:28,360
completed all the post 
processing. 

437
00:26:28,840 --> 00:26:32,080
Then we subsequently activated 
five countries in the main line.

438
00:26:32,480 --> 00:26:35,760
And that's when we realized that
when we try to rebase such a 

439
00:26:35,760 --> 00:26:39,840
huge change, be it in the form 
of number of countries and of 

440
00:26:39,840 --> 00:26:43,000
course some countries by itself 
themselves are complex and 

441
00:26:43,000 --> 00:26:47,360
therefore it needs more time. 
So it is important to rebase 

442
00:26:47,360 --> 00:26:52,120
periodically and not try to 
rebase in mass so that you don't

443
00:26:52,120 --> 00:26:54,600
end up with a lot of accumulated
config. 

444
00:26:55,600 --> 00:26:59,440
If you if you do that, it's 
possible that it could result in

445
00:26:59,440 --> 00:27:02,840
some error and may need 
involvement from the support 

446
00:27:02,840 --> 00:27:05,720
team from the back end. 
So that's the second learning we

447
00:27:05,720 --> 00:27:09,880
had in terms of how we can, how 
we can do it more frequently. 

448
00:27:09,880 --> 00:27:13,960
And the feature which Nicola 
mentioned about selective merge,

449
00:27:14,000 --> 00:27:16,880
I think that is something which 
will definitely benefit 

450
00:27:16,880 --> 00:27:21,640
customers because that will also
help address this, this 

451
00:27:21,640 --> 00:27:26,880
requirement of how do we avoid 
trying to do a merge with a 

452
00:27:26,880 --> 00:27:30,600
higher data set or a higher 
config or a higher code base. 

453
00:27:31,320 --> 00:27:36,200
And the third list given, we now
have the parallel line, we have 

454
00:27:36,200 --> 00:27:38,920
the main line. 
And then of course, all both the

455
00:27:38,920 --> 00:27:43,840
main lines and parallel lines 
undergo the periodic maintenance

456
00:27:43,840 --> 00:27:47,120
in the form of hotfix for which 
a calendar is already published 

457
00:27:47,120 --> 00:27:50,120
by SAP. 
It's important to consider that 

458
00:27:50,120 --> 00:27:55,040
calendar as well in doing these 
tasks, not just the project 

459
00:27:55,040 --> 00:27:59,720
timeline, because system 
availability will depend on that

460
00:27:59,720 --> 00:28:03,840
calendar as well and that may 
impact the ability to do certain

461
00:28:03,840 --> 00:28:06,720
tasks and therefore that should 
be considered. 

462
00:28:06,720 --> 00:28:11,280
So these are some three key 
learnings which we had and we 

463
00:28:11,280 --> 00:28:16,480
are incorporating that in 
subsequent phases of our project

464
00:28:16,480 --> 00:28:20,920
plan. 
And as we continue to use the 

465
00:28:20,920 --> 00:28:24,120
solution more, we will have more
learnings and we will continue 

466
00:28:24,600 --> 00:28:27,200
to evolve and adopt them. 
Thank you so much, Ajay. 

467
00:28:27,840 --> 00:28:31,360
Nicola, are there any other use 
cases where you see the parallel

468
00:28:31,360 --> 00:28:33,240
line being implemented 
successfully? 

469
00:28:33,680 --> 00:28:36,640
How do you envision other 
customers implementing the P the

470
00:28:36,640 --> 00:28:39,120
PL. in the future? 
Yes, Jerry. 

471
00:28:39,120 --> 00:28:43,240
So as you, as I told at the very
beginning, the parallel line was

472
00:28:43,280 --> 00:28:47,920
brought to the market and 
introduced to our customers via 

473
00:28:48,440 --> 00:28:52,640
a specific program called early 
adopter program in which 

474
00:28:52,640 --> 00:28:55,160
selected customers when 
enrolled. 

475
00:28:55,800 --> 00:28:59,600
Now what we noticed, what we 
have observed during this 

476
00:28:59,600 --> 00:29:04,480
program is that primarily 
customers enrolled asked to use 

477
00:29:04,480 --> 00:29:09,480
the parallel line in order to 
perform three specific use 

478
00:29:09,480 --> 00:29:12,560
cases. 
Having additional data migration

479
00:29:12,560 --> 00:29:17,720
run, having additional testing 
environment where to execute 

480
00:29:17,720 --> 00:29:22,080
testing activities and having a 
separate environment different 

481
00:29:22,080 --> 00:29:26,400
from the mainline tenants where 
also to execute training 

482
00:29:26,400 --> 00:29:31,760
sessions for the business users.
Now clearly also when we come to

483
00:29:31,760 --> 00:29:35,760
the data migration run, what 
they appreciated is also to 

484
00:29:35,760 --> 00:29:40,040
having repeating possibilities 
to perform the mocks, the data 

485
00:29:40,040 --> 00:29:44,160
migration mocks multiple times 
after having deleted and 

486
00:29:44,160 --> 00:29:46,200
recreated the parallel line 
anew. 

487
00:29:46,600 --> 00:29:51,440
Now this kind of consumption. 
So these three use cases which I

488
00:29:51,440 --> 00:29:55,080
described are totally in line 
with our expectation. 

489
00:29:55,600 --> 00:30:00,240
However, at the same time, what 
we expect now is to and. 

490
00:30:00,280 --> 00:30:04,240
And by the way, what's also our 
vision, our purpose why we 

491
00:30:04,240 --> 00:30:08,280
brought the parallel line to the
market is that customers can 

492
00:30:08,280 --> 00:30:13,560
perform a subsequent project 
waves having using the parallel 

493
00:30:13,560 --> 00:30:16,000
line for configuration 
extension. 

494
00:30:16,440 --> 00:30:20,080
It could be a new country, it 
could be a new org structure 

495
00:30:20,080 --> 00:30:23,800
like a company code. 
It could be a new scope or 

496
00:30:23,800 --> 00:30:27,200
bundle of scope items like a new
business process like 

497
00:30:27,200 --> 00:30:31,840
manufacturing, like procurement 
that was not implemented in Wave

498
00:30:31,840 --> 00:30:34,080
1. 
And they would like to implement

499
00:30:34,080 --> 00:30:37,720
that in Wave 2. 
And they do that before doing it

500
00:30:37,720 --> 00:30:41,160
in the main line, they do it in 
the parallel line and they can 

501
00:30:41,160 --> 00:30:44,960
have proper testing of these new
capabilities which are then 

502
00:30:45,080 --> 00:30:49,920
delivered to the in line and can
be combined with the life cycle 

503
00:30:50,160 --> 00:30:53,760
that is regularly innovating the
productive environment. 

504
00:30:54,120 --> 00:30:57,280
Thank you, Nicola. 
OK, I know we've covered a lot 

505
00:30:57,280 --> 00:30:58,840
of information here in our 
podcast. 

506
00:30:59,360 --> 00:31:02,120
Gentlemen, thank you. 
This has been a fascinating 

507
00:31:02,120 --> 00:31:04,640
discussion about the parallel 
line implementation methodology.

508
00:31:05,120 --> 00:31:08,000
We hope our listeners found it 
informative and are inspired to 

509
00:31:08,000 --> 00:31:10,160
consider the PL. for their 
future projects. 

510
00:31:10,680 --> 00:31:13,200
On a personal note, I want to 
thank each of you for taking the

511
00:31:13,200 --> 00:31:15,320
time and turning to our 
audience. 

512
00:31:15,320 --> 00:31:17,880
We want to thank you for joining
this episode and invite you to 

513
00:31:17,880 --> 00:31:22,760
subscribe to our podcast at 
sap.com/podcast, at Spotify, 

514
00:31:22,920 --> 00:31:26,000
Apple Podcast, or any audio 
platform you use to get your 

515
00:31:26,000 --> 00:31:28,440
notifications when new episodes 
are available. 

516
00:31:29,200 --> 00:31:31,480
And if you like this episode, 
don't forget to give us five 

517
00:31:31,480 --> 00:31:34,120
stars. 
You can reach us by e-mail at 

518
00:31:34,120 --> 00:31:39,840
insides4@sap.com or add us 
directly on LinkedIn TuneIn next

519
00:31:39,840 --> 00:31:42,440
time and be inside SAP S4 Honda 
Cloud.