1
00:00:00,720 --> 00:00:03,160
Hello and welcome to the ACT 
Pop. 

2
00:00:03,680 --> 00:00:06,320
This is the part of the show 
where we take a conversation 

3
00:00:06,320 --> 00:00:10,920
from the main episode and slow 
things down a bit, unpack some 

4
00:00:10,920 --> 00:00:14,320
of the terms and explain how the
nuclear industry actually works 

5
00:00:14,320 --> 00:00:17,200
behind the scenes. 
In the episode with Ahmed 

6
00:00:17,200 --> 00:00:20,400
Topanar from Bechdel, we talked 
about something that shows up 

7
00:00:20,400 --> 00:00:23,200
constantly in major 
infrastructure projects but 

8
00:00:23,200 --> 00:00:25,000
doesn't always get explained 
clearly. 

9
00:00:25,680 --> 00:00:30,200
That term is EPC. 
EPC stands for engineering, 

10
00:00:30,280 --> 00:00:34,240
procurement, and construction. 
If you've ever wondered who 

11
00:00:34,240 --> 00:00:37,800
actually builds a nuclear power 
plant, the answer usually 

12
00:00:37,800 --> 00:00:42,080
involves an EPC company. 
Utilities operate plants. 

13
00:00:42,320 --> 00:00:46,360
Reactor vendors design reactors.
Regulators license them. 

14
00:00:47,000 --> 00:00:50,960
But EPC companies are the ones 
who take the entire system and 

15
00:00:50,960 --> 00:00:52,720
physically bring it into 
reality. 

16
00:00:53,480 --> 00:00:57,560
They turn thousands of drawings,
analysis, safety systems and 

17
00:00:57,560 --> 00:01:01,720
regulatory requirements into 
concrete, steel, pipes, control 

18
00:01:01,720 --> 00:01:04,680
systems, and eventually a 
working power plant. 

19
00:01:05,160 --> 00:01:09,120
So today we're going to break 
down what an EPC actually means 

20
00:01:09,880 --> 00:01:13,320
and more importantly, why these 
companies are going to matter 

21
00:01:13,320 --> 00:01:17,440
enormously over the next two 
decades as the world tries to 

22
00:01:17,440 --> 00:01:22,240
build more nuclear plants Again,
First, engineering. 

23
00:01:22,680 --> 00:01:27,320
Let's start with the E In EPC, 
engineering is where the project

24
00:01:27,320 --> 00:01:31,160
becomes technically real. 
When a reactor vendor develops a

25
00:01:31,160 --> 00:01:34,800
design, whether that's a large 
reactor or a small modular 

26
00:01:34,800 --> 00:01:38,360
reactor, that design still has 
to be adapted to the specific 

27
00:01:38,360 --> 00:01:41,960
site where it will be built. 
That means engineers have to 

28
00:01:41,960 --> 00:01:45,480
answer questions like how does 
this reactor integrate with the 

29
00:01:45,480 --> 00:01:48,160
electrical grid? 
How will the cooling systems 

30
00:01:48,160 --> 00:01:49,920
interact with the local water 
source? 

31
00:01:50,520 --> 00:01:53,400
How do we design structures that
can withstand earthquakes, 

32
00:01:53,480 --> 00:01:57,480
floods, and extreme weather? 
How do we route thousands of 

33
00:01:57,480 --> 00:02:00,240
pipes, cables, and safety 
systems through the plant 

34
00:02:00,240 --> 00:02:01,920
without interfering with one 
another? 

35
00:02:02,560 --> 00:02:06,960
And in nuclear plants, this gets
extremely complex very quickly. 

36
00:02:08,080 --> 00:02:11,160
A single nuclear facility can 
contain 10s of thousands of 

37
00:02:11,160 --> 00:02:14,000
components and millions of 
individual parts. 

38
00:02:14,880 --> 00:02:17,800
That means all of the nuclear 
parts have to meet nuclear 

39
00:02:17,800 --> 00:02:21,160
safety standards, inventory 
requirements, and quality 

40
00:02:21,160 --> 00:02:24,400
assurance protocols. 
That means engineering isn't 

41
00:02:24,400 --> 00:02:26,840
just design, it's systems 
integration. 

42
00:02:27,400 --> 00:02:30,840
It's figuring out how mechanical
systems, electrical systems, 

43
00:02:30,960 --> 00:02:34,040
civil structures, 
instrumentation, and digital 

44
00:02:34,040 --> 00:02:38,200
controls all work together in a 
way that is safe, testable, and 

45
00:02:38,200 --> 00:02:40,920
licensable. 
And the better the engineering 

46
00:02:40,920 --> 00:02:43,920
is upfront, the smoother 
everything else goes later. 

47
00:02:45,240 --> 00:02:50,000
Next, procurement. 
Now we're on to the PE and EPC. 

48
00:02:50,680 --> 00:02:54,120
This is where the project turns 
from drawings into physical 

49
00:02:54,120 --> 00:02:57,240
components. 
Procurement involves sourcing 

50
00:02:57,240 --> 00:03:00,240
the massive list of equipment 
and materials needed to build 

51
00:03:00,240 --> 00:03:03,000
the plant. 
And for nuclear projects, this 

52
00:03:03,000 --> 00:03:05,080
is not like ordering office 
supplies. 

53
00:03:05,800 --> 00:03:08,280
These components can include 
things like reactor vessels, 

54
00:03:08,440 --> 00:03:11,760
steam generators, pumps and 
valves, control systems, 

55
00:03:12,040 --> 00:03:15,680
specialized piping, concrete 
structures, steel modules, and 

56
00:03:15,680 --> 00:03:17,880
electrical equipment, to name a 
few. 

57
00:03:18,680 --> 00:03:21,800
Many of these components require
specialized manufacturing, 

58
00:03:22,080 --> 00:03:26,360
sometimes years in advance. 
And because this is nuclear, 

59
00:03:27,000 --> 00:03:29,720
every component has to meet 
extremely strict quality 

60
00:03:29,720 --> 00:03:31,520
assurance and traceability 
standards. 

61
00:03:32,320 --> 00:03:34,960
You need to know where a 
material came from, how it was 

62
00:03:34,960 --> 00:03:38,560
fabricated, how it was tested, 
and how it was transported. 

63
00:03:39,200 --> 00:03:42,480
Procurement teams coordinate 
with manufacturers all over the 

64
00:03:42,480 --> 00:03:46,040
world to make sure these parts 
arrive at the right time, in the

65
00:03:46,040 --> 00:03:49,240
right order, and meet the 
required specifications. 

66
00:03:50,120 --> 00:03:53,680
If procurement slips up, 
construction can grind to a 

67
00:03:53,760 --> 00:03:56,440
halt. 
So this phase is actually about 

68
00:03:56,440 --> 00:03:59,760
supply chain orchestration at an
enormous scale. 

69
00:04:00,560 --> 00:04:03,720
If we're serious about building 
the next generation of nuclear 

70
00:04:03,720 --> 00:04:07,160
power plants, we need more than 
concrete and containment dones. 

71
00:04:07,600 --> 00:04:11,480
We need people. 
Engineers, welders, licensing 

72
00:04:11,480 --> 00:04:16,000
professionals, project managers,
Inc specialists, operators. 

73
00:04:16,320 --> 00:04:19,720
The people behind the build. 
That's where a nuclear talent 

74
00:04:19,720 --> 00:04:22,880
scout comes in. 
We source directly for companies

75
00:04:22,880 --> 00:04:26,200
to find the people who can 
actually move projects forward. 

76
00:04:26,680 --> 00:04:30,520
The ones who understand safety, 
culture, regulatory rigor, and 

77
00:04:30,520 --> 00:04:33,040
how to execute on time and on 
budget. 

78
00:04:33,720 --> 00:04:37,360
If you're ready to step into the
next phase of nuclear or you're 

79
00:04:37,360 --> 00:04:41,560
hiring for it, head over to 
nucleartownscout.com because the

80
00:04:41,560 --> 00:04:45,800
future of nuclear energy isn't 
just designed, it's staffed. 

81
00:04:46,720 --> 00:04:51,200
Now back to the show. 
Finally, construction. 

82
00:04:51,720 --> 00:04:54,000
That's where we reached the sea 
and EPC. 

83
00:04:54,920 --> 00:04:57,600
This is the phase most people 
picture when they think about 

84
00:04:57,600 --> 00:05:01,400
building a power plant. 
Huge cranes, concrete pores, 

85
00:05:01,640 --> 00:05:03,840
steel structures rising from the
ground. 

86
00:05:04,440 --> 00:05:08,080
But nuclear construction is also
one of the most precision driven

87
00:05:08,200 --> 00:05:10,160
construction environments in the
world. 

88
00:05:10,920 --> 00:05:14,360
Components have high tolerances 
measured in millimeters. 

89
00:05:15,120 --> 00:05:17,400
Installation must follow 
detailed procedures. 

90
00:05:17,840 --> 00:05:21,360
Welding inspections and testing 
are performed under strict 

91
00:05:21,440 --> 00:05:24,320
oversight. 
The sequencing matters a lot. 

92
00:05:25,120 --> 00:05:28,160
You can't install certain 
systems until the structures are

93
00:05:28,160 --> 00:05:30,680
complete. 
You can't energize electrical 

94
00:05:30,680 --> 00:05:33,200
systems until safety 
verifications are done. 

95
00:05:34,160 --> 00:05:37,560
You can't load nuclear fuel 
until an enormous amount of 

96
00:05:37,560 --> 00:05:40,160
checks and regulatory approvals 
are completed. 

97
00:05:40,960 --> 00:05:43,920
Construction is really the 
culmination of everything that 

98
00:05:43,920 --> 00:05:46,360
happened in the engineering and 
procurement phase. 

99
00:05:47,080 --> 00:05:50,320
It's where all of those plans 
and parts finally come together.

100
00:05:51,080 --> 00:05:56,480
So why does all of this matter? 
Because over the next two 

101
00:05:56,480 --> 00:06:00,680
decades, the world is going to 
need a lot more energy, which 

102
00:06:00,680 --> 00:06:03,560
means a lot more nuclear 
infrastructure. 

103
00:06:04,080 --> 00:06:08,000
Not just reactors, but the 
entire ecosystem around them. 

104
00:06:08,960 --> 00:06:12,360
If countries want clean, 
reliable electricity, industrial

105
00:06:12,360 --> 00:06:16,120
heat, hydrogen production, and 
potentially nuclear powered 

106
00:06:16,120 --> 00:06:19,200
shipping or remote energy 
systems, they will need 

107
00:06:19,200 --> 00:06:23,080
companies capable of executing 
extremely complex builds. 

108
00:06:24,000 --> 00:06:25,920
That's where EPC companies come 
in. 

109
00:06:26,520 --> 00:06:29,720
They provide the organizational 
capacity to manage massive 

110
00:06:29,720 --> 00:06:34,240
projects that involve thousands 
of workers, dozens or hundreds 

111
00:06:34,240 --> 00:06:38,480
of suppliers, complex regulatory
environments, and multi year 

112
00:06:38,480 --> 00:06:42,400
construction timelines. 
They coordinate engineers, craft

113
00:06:42,400 --> 00:06:46,440
workers, manufacturers, project 
managers, safety teams, and 

114
00:06:46,440 --> 00:06:49,200
regulators. 
And they do it while trying to 

115
00:06:49,200 --> 00:06:53,120
keep projects on schedule, on 
time, on budget. 

116
00:06:53,880 --> 00:06:57,160
Historically, nuclear 
construction slowed down in many

117
00:06:57,160 --> 00:07:00,320
countries over several decades, 
which means one of the 

118
00:07:00,320 --> 00:07:03,520
challenges now is rebuilding the
workforce and industrial 

119
00:07:03,520 --> 00:07:07,200
capability needed to deliver 
these projects consistently. 

120
00:07:07,720 --> 00:07:11,000
That includes licensing 
engineers, welders, project 

121
00:07:11,000 --> 00:07:13,160
managers, quality assurance 
specialists. 

122
00:07:13,320 --> 00:07:17,120
In other words, building nuclear
plants isn't just about reactor 

123
00:07:17,120 --> 00:07:20,080
technology, it's about 
industrial capacity. 

124
00:07:20,480 --> 00:07:23,440
There are a few trends that EPC 
companies are focusing on to 

125
00:07:23,440 --> 00:07:27,720
make future builds faster and 
more predictable. 1 is modular 

126
00:07:27,720 --> 00:07:30,480
construction. 
Instead of building everything 

127
00:07:30,480 --> 00:07:34,160
piece by piece at the site, 
larger components or entire 

128
00:07:34,160 --> 00:07:37,520
sections of the plant can be 
fabricated in factories, then 

129
00:07:37,520 --> 00:07:39,240
transported to the construction 
site. 

130
00:07:39,960 --> 00:07:43,640
That allows for higher quality 
control and potential shorter 

131
00:07:43,640 --> 00:07:47,240
construction timelines. 
Another area is digital 

132
00:07:47,240 --> 00:07:49,240
engineering and project 
management tools. 

133
00:07:50,040 --> 00:07:53,640
Modern modelling, simulation, 
and digital twin technologies 

134
00:07:54,080 --> 00:07:58,240
help teams coordinate design, 
track construction progress, and

135
00:07:58,240 --> 00:08:02,400
identify issues earlier. 
And finally, there's a big focus

136
00:08:02,400 --> 00:08:06,160
on standardization. 
If multiple plants use the same 

137
00:08:06,160 --> 00:08:09,960
reactor design and construction 
approach, teams can replicate 

138
00:08:09,960 --> 00:08:13,760
successful builds rather than 
reinventing the process every 

139
00:08:13,760 --> 00:08:17,000
single time. 
This is something countries like

140
00:08:17,000 --> 00:08:19,600
France and South Korea 
demonstrated in their earlier 

141
00:08:19,600 --> 00:08:22,960
waves of nuclear construction, 
and it's something many 

142
00:08:22,960 --> 00:08:27,040
developers are trying to return 
to as the industry grows again. 

143
00:08:27,840 --> 00:08:32,120
So when you hear the term EPC, 
remember that it represents the 

144
00:08:32,120 --> 00:08:36,200
full arc of bringing a nuclear 
project to life, engineering, 

145
00:08:36,640 --> 00:08:41,280
design and integrating the 
system's procurement, sourcing 

146
00:08:41,280 --> 00:08:45,280
the specialized components and 
construction, assembling the 

147
00:08:45,280 --> 00:08:49,600
facilities safely and precisely.
It's the bridge between reactor 

148
00:08:49,600 --> 00:08:53,520
innovation and actual power 
plants producing electricity on 

149
00:08:53,520 --> 00:08:56,080
the grid. 
And as the world looks towards 

150
00:08:56,080 --> 00:09:00,360
expanding nuclear energy in the 
future, EBC capability will be 

151
00:09:00,360 --> 00:09:03,240
one of the biggest factors 
determining how quickly and how 

152
00:09:03,240 --> 00:09:05,160
successfully those projects can 
happen. 

153
00:09:05,480 --> 00:09:08,240
If you want to hear the full 
episode with Ahmet Toknar from 

154
00:09:08,240 --> 00:09:11,360
Bechdel, check out the main 
episode where we go deeper into 

155
00:09:11,360 --> 00:09:14,720
how these projects are actually 
managed and what the future of 

156
00:09:14,720 --> 00:09:16,360
nuclear construction could look 
like. 

157
00:09:17,280 --> 00:09:20,200
On our next episode, we'll be 
hearing from a laborer and 

158
00:09:20,200 --> 00:09:23,520
welder who actually worked on 
Vogel Units 3 and 4. 

159
00:09:24,160 --> 00:09:26,440
Thank you so much for listening 
to Naked Iglier. 

160
00:09:26,760 --> 00:09:28,680
Until next time, stay curious.
