1
00:00:06,920 --> 00:00:09,480
William Haddon Junior, have you 
heard of that name? 

2
00:00:09,880 --> 00:00:15,080
If not but to use energy based 
hazard concepts or worked in Rd 

3
00:00:15,080 --> 00:00:19,160
safety, urbanomics or sports 
science, the chances are you've 

4
00:00:19,160 --> 00:00:21,000
directly been influenced by his 
work. 

5
00:00:21,560 --> 00:00:25,360
Haddon Junior was a hugely 
influential US researcher and 

6
00:00:25,360 --> 00:00:28,560
safety advocate, particularly in
Rd transport from the Sixties, 

7
00:00:28,560 --> 00:00:31,600
70s and 80s. 
Today is the first of a special 

8
00:00:31,600 --> 00:00:34,560
episode of say, FAZ. 
Let's call it a quick asode. 

9
00:00:35,080 --> 00:00:37,560
It won't make me feel a little 
weird, but let's roll with it. 

10
00:00:38,000 --> 00:00:41,320
In quick asodes I aim to capture
an interesting tool or concept 

11
00:00:41,320 --> 00:00:44,200
in an even more frantic and 
lower quality way than usual. 

12
00:00:45,520 --> 00:00:49,000
Hadn't established 10 measures 
for eliminating or mitigating 

13
00:00:49,000 --> 00:00:50,640
the exchange of hazardous 
energy. 

14
00:00:51,200 --> 00:00:53,680
In many ways I think it's 
superior to the hierarchy of 

15
00:00:53,680 --> 00:00:56,480
control. 
Let's apply it to a well known 

16
00:00:56,480 --> 00:01:01,120
area like fall prevention #1 
prevent the hazard from coming 

17
00:01:01,120 --> 00:01:03,760
into existence. 
This could be like designing 

18
00:01:03,760 --> 00:01:06,120
buildings with ground level 
access for tasks. 

19
00:01:06,720 --> 00:01:09,560
Use extendable tools or 
automation so work at hide is 

20
00:01:09,560 --> 00:01:13,120
not required. 
Or prefabricate assemblies at 

21
00:01:13,120 --> 00:01:15,520
ground level before insulation 
2. 

22
00:01:16,440 --> 00:01:19,240
Reduce the amount of hazard that
is brought into existence. 

23
00:01:19,520 --> 00:01:22,360
This could be limited hide 
exposure by lowering the working

24
00:01:22,360 --> 00:01:24,800
platforms. 
Where feasible, use portable 

25
00:01:24,800 --> 00:01:27,360
work stands instead of 
scaffolding where only small 

26
00:01:27,360 --> 00:01:31,000
elevation is needed and restrict
roof access points to only 

27
00:01:31,000 --> 00:01:35,080
essential personnel. 3 Prevent 
the release of the hazard that 

28
00:01:35,080 --> 00:01:38,320
already exists. 
Install guard rails and barriers

29
00:01:38,320 --> 00:01:42,160
around roof hedges and openings.
Use tow boards and safety gates 

30
00:01:42,160 --> 00:01:45,600
on ladders and scaffolds. 
Secure tools and materials to 

31
00:01:45,600 --> 00:01:49,680
prevent them from becoming 
falling objects. 4 Modify the 

32
00:01:49,680 --> 00:01:52,720
rate or spatial distribution of 
release of the hazard. 

33
00:01:53,680 --> 00:01:56,920
So use controlled descent 
systems or slow moving lifts to 

34
00:01:56,920 --> 00:02:00,680
prevent sudden drops. 
Place staging areas further from

35
00:02:00,680 --> 00:02:04,840
edges to keep workers away from 
the fall zone, or install work 

36
00:02:04,840 --> 00:02:08,400
positioning systems to limit 
movement into hazardous zones 5.

37
00:02:09,039 --> 00:02:12,560
Separate in time or space the 
hazard from that which is to be 

38
00:02:12,560 --> 00:02:15,280
protected. 
So schedule work at heights when

39
00:02:15,280 --> 00:02:18,440
fewer people are on site. 
Below as in reducing the risk of

40
00:02:18,440 --> 00:02:21,920
dropped object injuries. 
Keep unrelated workers out of 

41
00:02:21,920 --> 00:02:25,200
the fall zones using exclusion 
zones in signage. 6. 

42
00:02:25,760 --> 00:02:28,520
Separate the hazard from that 
which is to be protected by 

43
00:02:28,520 --> 00:02:31,600
material barrier. 
So use scaffolding with full 

44
00:02:31,600 --> 00:02:35,120
enclosures with mesh or netting.
Fit skylight covers to prevent 

45
00:02:35,120 --> 00:02:38,640
fall through fragile roofs. 
Install safety Nets under 

46
00:02:38,640 --> 00:02:43,320
elevated web platforms 7. 
Modify relevant basic qualities 

47
00:02:43,320 --> 00:02:46,840
of the hazard though use non 
slip surfaces and platforms to 

48
00:02:46,840 --> 00:02:50,040
reduce slip likelihood. 
Reduce platform heights where 

49
00:02:50,040 --> 00:02:51,920
possible. 
You know like step stools 

50
00:02:51,920 --> 00:02:55,000
instead of ladders. 
Ensure ladders are wide based 

51
00:02:55,000 --> 00:02:58,800
and have stabilising feet. 8 
Make what is to be protected 

52
00:02:58,800 --> 00:03:01,200
more resistant to damage. 
A little bit harder when it 

53
00:03:01,200 --> 00:03:04,200
involves people but maybe 
require personal fall arrest 

54
00:03:04,200 --> 00:03:05,760
systems. 
You know full body harness and 

55
00:03:05,760 --> 00:03:09,400
lanyard shock absorbing lanyards
to reduce impact forces. 

56
00:03:10,080 --> 00:03:13,800
Train workers in fall arrest 
self rescue techniques. 9 

57
00:03:14,320 --> 00:03:16,400
Counter the damage already done 
by the hazard. 

58
00:03:16,760 --> 00:03:19,880
Provide immediate rescue plans 
for the suspended workers. 

59
00:03:20,200 --> 00:03:22,720
Ensure on site first datas are 
trained in trauma and 

60
00:03:22,720 --> 00:03:25,680
suspension, trauma treatment and
having emergency response groups

61
00:03:26,240 --> 00:03:29,960
10 Stabilise, repair and 
rehabilitate the object of 

62
00:03:29,960 --> 00:03:32,280
damage. 
So offering medical 

63
00:03:32,280 --> 00:03:35,800
rehabilitation programmes for 
injured workers and adapting 

64
00:03:35,800 --> 00:03:39,040
roles to suit partial recovery 
while maintaining employment. 

65
00:03:39,440 --> 00:03:42,560
Now, it doesn't perfectly align 
with all of the known factors of

66
00:03:42,560 --> 00:03:46,280
hazard interactions and 
incidents, your psychosocial 

67
00:03:46,280 --> 00:03:49,800
factors, and let's not go into 
mental or psychological energy, 

68
00:03:49,800 --> 00:03:52,160
please. 
But it doesn't need to either. 

69
00:03:52,520 --> 00:03:56,080
It helps provide one structured 
process for one slice of the 

70
00:03:56,080 --> 00:03:59,160
hazardous energy pie. 
Why not give it a go and let me 

71
00:03:59,160 --> 00:04:02,400
know how you find it compared to
or in conjunction with the 

72
00:04:02,400 --> 00:04:05,520
hierarchy of controls? 
That's it on this quicker side 

73
00:04:05,520 --> 00:04:07,000
of safe as. 
Thanks everyone.